New Calgary Cancer Centre (NCCC)


Calgary, Canada

BFCA was contracted by PCL Construction Management for the design & installation of a temporary shoring system with soldier piles and timber lagging retaining up to 18m height and the overall quantity was approx. 12,000m2. For the soldier pile installation works BFCA used 2 BAUER BG28 piling rigs. As horizontal support of the shoring works BFCA also installed more than 1,000 temporary anchors utilizing up to 4 Klemm tie-back drilling rigs.

In addition to the shoring works BFCA drilled 90 foundation piles up to 1,650mm straight shaft diameter with 4,500mm dia belled up to a depth of 25m.